Defining terms: man hours vs. calendar hours [closed]

The name of the pictureThe name of the pictureThe name of the pictureClash Royale CLAN TAG#URR8PPP





.everyoneloves__top-leaderboard:empty,.everyoneloves__mid-leaderboard:empty margin-bottom:0;







up vote
2
down vote

favorite












I find myself regularly expressing project schedules using two terms. I have made up one of them and it is clear to my listeners what I mean. However, I suspect that more common terms exist for these items.



The terms are:



  • Working hours - This is a statement of actual or estimated working hours. For example a "40 hour" project. I think the common term for this is "man hours"

  • Calendar time - This is how long a project takes in terms of dates. As in, "I'll have it by next Tuesday". I do not know the term for this.

These terms are applied in the context of, "This is a 20 hour task and based on my schedule it will be completed in one week.". This shows the effort involved as well as the scheduling aspect.



What are the correct or widely used terms for these concepts?



To clarify - I am NOT asking about the conversion and application of man-hours vs. calendar-time. I simply want to make sure I am using the right nouns for those two concepts.







share|improve this question













closed as primarily opinion-based by gnat, Chris E, Mister Positive, JasonJ, Michael Grubey Mar 3 '17 at 4:29


Many good questions generate some degree of opinion based on expert experience, but answers to this question will tend to be almost entirely based on opinions, rather than facts, references, or specific expertise. If this question can be reworded to fit the rules in the help center, please edit the question.










  • 4




    Those are common terms. And a major misconception is a calendar week = man week. Any job has administrative overhead
    – paparazzo
    Jun 20 '16 at 18:52










  • I often use "wall-clock time" to refer to "calendar time."
    – Ernest Friedman-Hill
    Jun 20 '16 at 19:35










  • We usually use the terms man-hours and project due date. Be sure when figuring the due date to not allow 8 or more hours per person in per day in work hours. YOu need to only allow 80% to account for leave (both planned and unexepected like bereavement leave), administrativcee work, unavoidable delay, and people being pulled off temporearil;y for other projects or production issues or required HR trainiendg etc.
    – HLGEM
    Jun 20 '16 at 20:31






  • 1




    man-hours is very common. see: en.wikipedia.org/wiki/Man-hour
    – WorkerDrone
    Jun 20 '16 at 20:38











  • Instead of "calendar time" I would suggest "Due date" for what you described.
    – Brandin
    Jun 20 '16 at 23:33
















up vote
2
down vote

favorite












I find myself regularly expressing project schedules using two terms. I have made up one of them and it is clear to my listeners what I mean. However, I suspect that more common terms exist for these items.



The terms are:



  • Working hours - This is a statement of actual or estimated working hours. For example a "40 hour" project. I think the common term for this is "man hours"

  • Calendar time - This is how long a project takes in terms of dates. As in, "I'll have it by next Tuesday". I do not know the term for this.

These terms are applied in the context of, "This is a 20 hour task and based on my schedule it will be completed in one week.". This shows the effort involved as well as the scheduling aspect.



What are the correct or widely used terms for these concepts?



To clarify - I am NOT asking about the conversion and application of man-hours vs. calendar-time. I simply want to make sure I am using the right nouns for those two concepts.







share|improve this question













closed as primarily opinion-based by gnat, Chris E, Mister Positive, JasonJ, Michael Grubey Mar 3 '17 at 4:29


Many good questions generate some degree of opinion based on expert experience, but answers to this question will tend to be almost entirely based on opinions, rather than facts, references, or specific expertise. If this question can be reworded to fit the rules in the help center, please edit the question.










  • 4




    Those are common terms. And a major misconception is a calendar week = man week. Any job has administrative overhead
    – paparazzo
    Jun 20 '16 at 18:52










  • I often use "wall-clock time" to refer to "calendar time."
    – Ernest Friedman-Hill
    Jun 20 '16 at 19:35










  • We usually use the terms man-hours and project due date. Be sure when figuring the due date to not allow 8 or more hours per person in per day in work hours. YOu need to only allow 80% to account for leave (both planned and unexepected like bereavement leave), administrativcee work, unavoidable delay, and people being pulled off temporearil;y for other projects or production issues or required HR trainiendg etc.
    – HLGEM
    Jun 20 '16 at 20:31






  • 1




    man-hours is very common. see: en.wikipedia.org/wiki/Man-hour
    – WorkerDrone
    Jun 20 '16 at 20:38











  • Instead of "calendar time" I would suggest "Due date" for what you described.
    – Brandin
    Jun 20 '16 at 23:33












up vote
2
down vote

favorite









up vote
2
down vote

favorite











I find myself regularly expressing project schedules using two terms. I have made up one of them and it is clear to my listeners what I mean. However, I suspect that more common terms exist for these items.



The terms are:



  • Working hours - This is a statement of actual or estimated working hours. For example a "40 hour" project. I think the common term for this is "man hours"

  • Calendar time - This is how long a project takes in terms of dates. As in, "I'll have it by next Tuesday". I do not know the term for this.

These terms are applied in the context of, "This is a 20 hour task and based on my schedule it will be completed in one week.". This shows the effort involved as well as the scheduling aspect.



What are the correct or widely used terms for these concepts?



To clarify - I am NOT asking about the conversion and application of man-hours vs. calendar-time. I simply want to make sure I am using the right nouns for those two concepts.







share|improve this question













I find myself regularly expressing project schedules using two terms. I have made up one of them and it is clear to my listeners what I mean. However, I suspect that more common terms exist for these items.



The terms are:



  • Working hours - This is a statement of actual or estimated working hours. For example a "40 hour" project. I think the common term for this is "man hours"

  • Calendar time - This is how long a project takes in terms of dates. As in, "I'll have it by next Tuesday". I do not know the term for this.

These terms are applied in the context of, "This is a 20 hour task and based on my schedule it will be completed in one week.". This shows the effort involved as well as the scheduling aspect.



What are the correct or widely used terms for these concepts?



To clarify - I am NOT asking about the conversion and application of man-hours vs. calendar-time. I simply want to make sure I am using the right nouns for those two concepts.









share|improve this question












share|improve this question




share|improve this question








edited Jun 21 '16 at 13:33
























asked Jun 20 '16 at 18:46









Freiheit

583218




583218




closed as primarily opinion-based by gnat, Chris E, Mister Positive, JasonJ, Michael Grubey Mar 3 '17 at 4:29


Many good questions generate some degree of opinion based on expert experience, but answers to this question will tend to be almost entirely based on opinions, rather than facts, references, or specific expertise. If this question can be reworded to fit the rules in the help center, please edit the question.






closed as primarily opinion-based by gnat, Chris E, Mister Positive, JasonJ, Michael Grubey Mar 3 '17 at 4:29


Many good questions generate some degree of opinion based on expert experience, but answers to this question will tend to be almost entirely based on opinions, rather than facts, references, or specific expertise. If this question can be reworded to fit the rules in the help center, please edit the question.









  • 4




    Those are common terms. And a major misconception is a calendar week = man week. Any job has administrative overhead
    – paparazzo
    Jun 20 '16 at 18:52










  • I often use "wall-clock time" to refer to "calendar time."
    – Ernest Friedman-Hill
    Jun 20 '16 at 19:35










  • We usually use the terms man-hours and project due date. Be sure when figuring the due date to not allow 8 or more hours per person in per day in work hours. YOu need to only allow 80% to account for leave (both planned and unexepected like bereavement leave), administrativcee work, unavoidable delay, and people being pulled off temporearil;y for other projects or production issues or required HR trainiendg etc.
    – HLGEM
    Jun 20 '16 at 20:31






  • 1




    man-hours is very common. see: en.wikipedia.org/wiki/Man-hour
    – WorkerDrone
    Jun 20 '16 at 20:38











  • Instead of "calendar time" I would suggest "Due date" for what you described.
    – Brandin
    Jun 20 '16 at 23:33












  • 4




    Those are common terms. And a major misconception is a calendar week = man week. Any job has administrative overhead
    – paparazzo
    Jun 20 '16 at 18:52










  • I often use "wall-clock time" to refer to "calendar time."
    – Ernest Friedman-Hill
    Jun 20 '16 at 19:35










  • We usually use the terms man-hours and project due date. Be sure when figuring the due date to not allow 8 or more hours per person in per day in work hours. YOu need to only allow 80% to account for leave (both planned and unexepected like bereavement leave), administrativcee work, unavoidable delay, and people being pulled off temporearil;y for other projects or production issues or required HR trainiendg etc.
    – HLGEM
    Jun 20 '16 at 20:31






  • 1




    man-hours is very common. see: en.wikipedia.org/wiki/Man-hour
    – WorkerDrone
    Jun 20 '16 at 20:38











  • Instead of "calendar time" I would suggest "Due date" for what you described.
    – Brandin
    Jun 20 '16 at 23:33







4




4




Those are common terms. And a major misconception is a calendar week = man week. Any job has administrative overhead
– paparazzo
Jun 20 '16 at 18:52




Those are common terms. And a major misconception is a calendar week = man week. Any job has administrative overhead
– paparazzo
Jun 20 '16 at 18:52












I often use "wall-clock time" to refer to "calendar time."
– Ernest Friedman-Hill
Jun 20 '16 at 19:35




I often use "wall-clock time" to refer to "calendar time."
– Ernest Friedman-Hill
Jun 20 '16 at 19:35












We usually use the terms man-hours and project due date. Be sure when figuring the due date to not allow 8 or more hours per person in per day in work hours. YOu need to only allow 80% to account for leave (both planned and unexepected like bereavement leave), administrativcee work, unavoidable delay, and people being pulled off temporearil;y for other projects or production issues or required HR trainiendg etc.
– HLGEM
Jun 20 '16 at 20:31




We usually use the terms man-hours and project due date. Be sure when figuring the due date to not allow 8 or more hours per person in per day in work hours. YOu need to only allow 80% to account for leave (both planned and unexepected like bereavement leave), administrativcee work, unavoidable delay, and people being pulled off temporearil;y for other projects or production issues or required HR trainiendg etc.
– HLGEM
Jun 20 '16 at 20:31




1




1




man-hours is very common. see: en.wikipedia.org/wiki/Man-hour
– WorkerDrone
Jun 20 '16 at 20:38





man-hours is very common. see: en.wikipedia.org/wiki/Man-hour
– WorkerDrone
Jun 20 '16 at 20:38













Instead of "calendar time" I would suggest "Due date" for what you described.
– Brandin
Jun 20 '16 at 23:33




Instead of "calendar time" I would suggest "Due date" for what you described.
– Brandin
Jun 20 '16 at 23:33










4 Answers
4






active

oldest

votes

















up vote
5
down vote



accepted










Man hours are correct for your working hours however be careful that these are multiplied by the number of people working. For example a team of 5 working for an 8 hour day on a project contributes 40 man hours.



Duration or wrap up date can be used to discuss your calendar time depending on context.



Taking your example "This is a 20 man hour task and based on my schedule it will have a one week duration" sounds quite natural to me but "This is a 20 man hour task and based on my schedule our wrap up date is projected to be June 28th" would also be fine.






share|improve this answer























  • You won't get 40 hours actual work with 5 people working an 8 hour day...
    – HorusKol
    Jun 21 '16 at 14:15






  • 1




    @HorusKol Was just about to comment on your answer. The preferred method when I studied this in university was that your task time was padded to included 20-25% of non-focused work. So a 40 man hour estimate would be 32-34 hours of active work and 6-8 hours of breaks/meetings/random paperwork.
    – Myles
    Jun 21 '16 at 14:18







  • 1




    I guess it comes to the same result - but I prefer to not pad a task time (because then I know a 1 hour task will take 1 hour), and simply acknowledge that 1/3 of a working day will not be "on-task".
    – HorusKol
    Jun 21 '16 at 23:30

















up vote
2
down vote













Man-hours is correct for the amount of effort required by one worker.



The problem comes with conversion to calendar time for deadlines.



It is very easy to think that a 40-hour project can be done in one work by a worker who is contract for 8-hour days. But then that worker has to get a a couple of coffees, probably go to the toilet a few times, and take a break (even if just sitting as his desk) every hour or so. Not to mention people coming in with questions, email, setting up appointments, and meetings (related and unrelated). Then there's overhead whenever you start adding more developers to a project team, since they have to communicate with each other about what they're doing.



Plus, there's typically other work involved around the project that doesn't get included in the working time estimate.



All this means is that you can't divide by 8 hours to get the calendar time for a project.



After a bit of trial and error over the years, I've found assuming 5 hours of on-task activity per day gives a pretty fair estimate (we work 7.5 hour days [8 hours if you include a lunch break]).



So, a 40-hour project will be completed in 8 days by one person.






share|improve this answer




























    up vote
    1
    down vote













    What you are describing is the different terminology between effort and schedule. As others have answered, schedule has to incorporate some level of overhead, as well as individual leave arrangements, public holidays, staff rolling off/on etc...



    There are a number of variants on this, and probably the most prevalent are already in your question, but in the software development community common terms for effort are:



    • ideal hours

    • story points

    • effort hours

    • estimated effort (hours)

    ...whilst schedules either directly refer to the calendar, or use terms like working days.






    share|improve this answer




























      up vote
      -1
      down vote













      Work hours are for time to complete task or project by each team or individual. Calendar hours or time is for the whole combined hours of all individuals and processes needed over a period of time to complete more than one project to reach a goal by the end of a predefined cycle or timeline. I.e. Quarterly or Annual or reporting. The shortest way to put this is Calendar hours are the combined hours of full time and near full time employees each month of the previous year then averaged for the year to determine "service hours"
      I searched under Calendar hours/reporting for applicable large employers. This formula is also used to determine employee benefits or employer responsibility and a similar definition is used to determine students credit hours or even professional qualifications.






      share|improve this answer



















      • 1




        is this merely your opinion or you can back it up somehow?
        – gnat
        Mar 2 '17 at 13:48










      • I don't have definitive proof. This is similar to a method That I used myself in construction.
        – C.E.B
        Mar 2 '17 at 13:55

















      4 Answers
      4






      active

      oldest

      votes








      4 Answers
      4






      active

      oldest

      votes









      active

      oldest

      votes






      active

      oldest

      votes








      up vote
      5
      down vote



      accepted










      Man hours are correct for your working hours however be careful that these are multiplied by the number of people working. For example a team of 5 working for an 8 hour day on a project contributes 40 man hours.



      Duration or wrap up date can be used to discuss your calendar time depending on context.



      Taking your example "This is a 20 man hour task and based on my schedule it will have a one week duration" sounds quite natural to me but "This is a 20 man hour task and based on my schedule our wrap up date is projected to be June 28th" would also be fine.






      share|improve this answer























      • You won't get 40 hours actual work with 5 people working an 8 hour day...
        – HorusKol
        Jun 21 '16 at 14:15






      • 1




        @HorusKol Was just about to comment on your answer. The preferred method when I studied this in university was that your task time was padded to included 20-25% of non-focused work. So a 40 man hour estimate would be 32-34 hours of active work and 6-8 hours of breaks/meetings/random paperwork.
        – Myles
        Jun 21 '16 at 14:18







      • 1




        I guess it comes to the same result - but I prefer to not pad a task time (because then I know a 1 hour task will take 1 hour), and simply acknowledge that 1/3 of a working day will not be "on-task".
        – HorusKol
        Jun 21 '16 at 23:30














      up vote
      5
      down vote



      accepted










      Man hours are correct for your working hours however be careful that these are multiplied by the number of people working. For example a team of 5 working for an 8 hour day on a project contributes 40 man hours.



      Duration or wrap up date can be used to discuss your calendar time depending on context.



      Taking your example "This is a 20 man hour task and based on my schedule it will have a one week duration" sounds quite natural to me but "This is a 20 man hour task and based on my schedule our wrap up date is projected to be June 28th" would also be fine.






      share|improve this answer























      • You won't get 40 hours actual work with 5 people working an 8 hour day...
        – HorusKol
        Jun 21 '16 at 14:15






      • 1




        @HorusKol Was just about to comment on your answer. The preferred method when I studied this in university was that your task time was padded to included 20-25% of non-focused work. So a 40 man hour estimate would be 32-34 hours of active work and 6-8 hours of breaks/meetings/random paperwork.
        – Myles
        Jun 21 '16 at 14:18







      • 1




        I guess it comes to the same result - but I prefer to not pad a task time (because then I know a 1 hour task will take 1 hour), and simply acknowledge that 1/3 of a working day will not be "on-task".
        – HorusKol
        Jun 21 '16 at 23:30












      up vote
      5
      down vote



      accepted







      up vote
      5
      down vote



      accepted






      Man hours are correct for your working hours however be careful that these are multiplied by the number of people working. For example a team of 5 working for an 8 hour day on a project contributes 40 man hours.



      Duration or wrap up date can be used to discuss your calendar time depending on context.



      Taking your example "This is a 20 man hour task and based on my schedule it will have a one week duration" sounds quite natural to me but "This is a 20 man hour task and based on my schedule our wrap up date is projected to be June 28th" would also be fine.






      share|improve this answer















      Man hours are correct for your working hours however be careful that these are multiplied by the number of people working. For example a team of 5 working for an 8 hour day on a project contributes 40 man hours.



      Duration or wrap up date can be used to discuss your calendar time depending on context.



      Taking your example "This is a 20 man hour task and based on my schedule it will have a one week duration" sounds quite natural to me but "This is a 20 man hour task and based on my schedule our wrap up date is projected to be June 28th" would also be fine.







      share|improve this answer















      share|improve this answer



      share|improve this answer








      edited Jun 20 '16 at 20:33


























      answered Jun 20 '16 at 19:16









      Myles

      25.4k658104




      25.4k658104











      • You won't get 40 hours actual work with 5 people working an 8 hour day...
        – HorusKol
        Jun 21 '16 at 14:15






      • 1




        @HorusKol Was just about to comment on your answer. The preferred method when I studied this in university was that your task time was padded to included 20-25% of non-focused work. So a 40 man hour estimate would be 32-34 hours of active work and 6-8 hours of breaks/meetings/random paperwork.
        – Myles
        Jun 21 '16 at 14:18







      • 1




        I guess it comes to the same result - but I prefer to not pad a task time (because then I know a 1 hour task will take 1 hour), and simply acknowledge that 1/3 of a working day will not be "on-task".
        – HorusKol
        Jun 21 '16 at 23:30
















      • You won't get 40 hours actual work with 5 people working an 8 hour day...
        – HorusKol
        Jun 21 '16 at 14:15






      • 1




        @HorusKol Was just about to comment on your answer. The preferred method when I studied this in university was that your task time was padded to included 20-25% of non-focused work. So a 40 man hour estimate would be 32-34 hours of active work and 6-8 hours of breaks/meetings/random paperwork.
        – Myles
        Jun 21 '16 at 14:18







      • 1




        I guess it comes to the same result - but I prefer to not pad a task time (because then I know a 1 hour task will take 1 hour), and simply acknowledge that 1/3 of a working day will not be "on-task".
        – HorusKol
        Jun 21 '16 at 23:30















      You won't get 40 hours actual work with 5 people working an 8 hour day...
      – HorusKol
      Jun 21 '16 at 14:15




      You won't get 40 hours actual work with 5 people working an 8 hour day...
      – HorusKol
      Jun 21 '16 at 14:15




      1




      1




      @HorusKol Was just about to comment on your answer. The preferred method when I studied this in university was that your task time was padded to included 20-25% of non-focused work. So a 40 man hour estimate would be 32-34 hours of active work and 6-8 hours of breaks/meetings/random paperwork.
      – Myles
      Jun 21 '16 at 14:18





      @HorusKol Was just about to comment on your answer. The preferred method when I studied this in university was that your task time was padded to included 20-25% of non-focused work. So a 40 man hour estimate would be 32-34 hours of active work and 6-8 hours of breaks/meetings/random paperwork.
      – Myles
      Jun 21 '16 at 14:18





      1




      1




      I guess it comes to the same result - but I prefer to not pad a task time (because then I know a 1 hour task will take 1 hour), and simply acknowledge that 1/3 of a working day will not be "on-task".
      – HorusKol
      Jun 21 '16 at 23:30




      I guess it comes to the same result - but I prefer to not pad a task time (because then I know a 1 hour task will take 1 hour), and simply acknowledge that 1/3 of a working day will not be "on-task".
      – HorusKol
      Jun 21 '16 at 23:30












      up vote
      2
      down vote













      Man-hours is correct for the amount of effort required by one worker.



      The problem comes with conversion to calendar time for deadlines.



      It is very easy to think that a 40-hour project can be done in one work by a worker who is contract for 8-hour days. But then that worker has to get a a couple of coffees, probably go to the toilet a few times, and take a break (even if just sitting as his desk) every hour or so. Not to mention people coming in with questions, email, setting up appointments, and meetings (related and unrelated). Then there's overhead whenever you start adding more developers to a project team, since they have to communicate with each other about what they're doing.



      Plus, there's typically other work involved around the project that doesn't get included in the working time estimate.



      All this means is that you can't divide by 8 hours to get the calendar time for a project.



      After a bit of trial and error over the years, I've found assuming 5 hours of on-task activity per day gives a pretty fair estimate (we work 7.5 hour days [8 hours if you include a lunch break]).



      So, a 40-hour project will be completed in 8 days by one person.






      share|improve this answer

























        up vote
        2
        down vote













        Man-hours is correct for the amount of effort required by one worker.



        The problem comes with conversion to calendar time for deadlines.



        It is very easy to think that a 40-hour project can be done in one work by a worker who is contract for 8-hour days. But then that worker has to get a a couple of coffees, probably go to the toilet a few times, and take a break (even if just sitting as his desk) every hour or so. Not to mention people coming in with questions, email, setting up appointments, and meetings (related and unrelated). Then there's overhead whenever you start adding more developers to a project team, since they have to communicate with each other about what they're doing.



        Plus, there's typically other work involved around the project that doesn't get included in the working time estimate.



        All this means is that you can't divide by 8 hours to get the calendar time for a project.



        After a bit of trial and error over the years, I've found assuming 5 hours of on-task activity per day gives a pretty fair estimate (we work 7.5 hour days [8 hours if you include a lunch break]).



        So, a 40-hour project will be completed in 8 days by one person.






        share|improve this answer























          up vote
          2
          down vote










          up vote
          2
          down vote









          Man-hours is correct for the amount of effort required by one worker.



          The problem comes with conversion to calendar time for deadlines.



          It is very easy to think that a 40-hour project can be done in one work by a worker who is contract for 8-hour days. But then that worker has to get a a couple of coffees, probably go to the toilet a few times, and take a break (even if just sitting as his desk) every hour or so. Not to mention people coming in with questions, email, setting up appointments, and meetings (related and unrelated). Then there's overhead whenever you start adding more developers to a project team, since they have to communicate with each other about what they're doing.



          Plus, there's typically other work involved around the project that doesn't get included in the working time estimate.



          All this means is that you can't divide by 8 hours to get the calendar time for a project.



          After a bit of trial and error over the years, I've found assuming 5 hours of on-task activity per day gives a pretty fair estimate (we work 7.5 hour days [8 hours if you include a lunch break]).



          So, a 40-hour project will be completed in 8 days by one person.






          share|improve this answer













          Man-hours is correct for the amount of effort required by one worker.



          The problem comes with conversion to calendar time for deadlines.



          It is very easy to think that a 40-hour project can be done in one work by a worker who is contract for 8-hour days. But then that worker has to get a a couple of coffees, probably go to the toilet a few times, and take a break (even if just sitting as his desk) every hour or so. Not to mention people coming in with questions, email, setting up appointments, and meetings (related and unrelated). Then there's overhead whenever you start adding more developers to a project team, since they have to communicate with each other about what they're doing.



          Plus, there's typically other work involved around the project that doesn't get included in the working time estimate.



          All this means is that you can't divide by 8 hours to get the calendar time for a project.



          After a bit of trial and error over the years, I've found assuming 5 hours of on-task activity per day gives a pretty fair estimate (we work 7.5 hour days [8 hours if you include a lunch break]).



          So, a 40-hour project will be completed in 8 days by one person.







          share|improve this answer













          share|improve this answer



          share|improve this answer











          answered Jun 21 '16 at 0:30









          HorusKol

          16.3k63267




          16.3k63267




















              up vote
              1
              down vote













              What you are describing is the different terminology between effort and schedule. As others have answered, schedule has to incorporate some level of overhead, as well as individual leave arrangements, public holidays, staff rolling off/on etc...



              There are a number of variants on this, and probably the most prevalent are already in your question, but in the software development community common terms for effort are:



              • ideal hours

              • story points

              • effort hours

              • estimated effort (hours)

              ...whilst schedules either directly refer to the calendar, or use terms like working days.






              share|improve this answer

























                up vote
                1
                down vote













                What you are describing is the different terminology between effort and schedule. As others have answered, schedule has to incorporate some level of overhead, as well as individual leave arrangements, public holidays, staff rolling off/on etc...



                There are a number of variants on this, and probably the most prevalent are already in your question, but in the software development community common terms for effort are:



                • ideal hours

                • story points

                • effort hours

                • estimated effort (hours)

                ...whilst schedules either directly refer to the calendar, or use terms like working days.






                share|improve this answer























                  up vote
                  1
                  down vote










                  up vote
                  1
                  down vote









                  What you are describing is the different terminology between effort and schedule. As others have answered, schedule has to incorporate some level of overhead, as well as individual leave arrangements, public holidays, staff rolling off/on etc...



                  There are a number of variants on this, and probably the most prevalent are already in your question, but in the software development community common terms for effort are:



                  • ideal hours

                  • story points

                  • effort hours

                  • estimated effort (hours)

                  ...whilst schedules either directly refer to the calendar, or use terms like working days.






                  share|improve this answer













                  What you are describing is the different terminology between effort and schedule. As others have answered, schedule has to incorporate some level of overhead, as well as individual leave arrangements, public holidays, staff rolling off/on etc...



                  There are a number of variants on this, and probably the most prevalent are already in your question, but in the software development community common terms for effort are:



                  • ideal hours

                  • story points

                  • effort hours

                  • estimated effort (hours)

                  ...whilst schedules either directly refer to the calendar, or use terms like working days.







                  share|improve this answer













                  share|improve this answer



                  share|improve this answer











                  answered Mar 2 '17 at 6:08









                  piers7

                  1192




                  1192




















                      up vote
                      -1
                      down vote













                      Work hours are for time to complete task or project by each team or individual. Calendar hours or time is for the whole combined hours of all individuals and processes needed over a period of time to complete more than one project to reach a goal by the end of a predefined cycle or timeline. I.e. Quarterly or Annual or reporting. The shortest way to put this is Calendar hours are the combined hours of full time and near full time employees each month of the previous year then averaged for the year to determine "service hours"
                      I searched under Calendar hours/reporting for applicable large employers. This formula is also used to determine employee benefits or employer responsibility and a similar definition is used to determine students credit hours or even professional qualifications.






                      share|improve this answer



















                      • 1




                        is this merely your opinion or you can back it up somehow?
                        – gnat
                        Mar 2 '17 at 13:48










                      • I don't have definitive proof. This is similar to a method That I used myself in construction.
                        – C.E.B
                        Mar 2 '17 at 13:55














                      up vote
                      -1
                      down vote













                      Work hours are for time to complete task or project by each team or individual. Calendar hours or time is for the whole combined hours of all individuals and processes needed over a period of time to complete more than one project to reach a goal by the end of a predefined cycle or timeline. I.e. Quarterly or Annual or reporting. The shortest way to put this is Calendar hours are the combined hours of full time and near full time employees each month of the previous year then averaged for the year to determine "service hours"
                      I searched under Calendar hours/reporting for applicable large employers. This formula is also used to determine employee benefits or employer responsibility and a similar definition is used to determine students credit hours or even professional qualifications.






                      share|improve this answer



















                      • 1




                        is this merely your opinion or you can back it up somehow?
                        – gnat
                        Mar 2 '17 at 13:48










                      • I don't have definitive proof. This is similar to a method That I used myself in construction.
                        – C.E.B
                        Mar 2 '17 at 13:55












                      up vote
                      -1
                      down vote










                      up vote
                      -1
                      down vote









                      Work hours are for time to complete task or project by each team or individual. Calendar hours or time is for the whole combined hours of all individuals and processes needed over a period of time to complete more than one project to reach a goal by the end of a predefined cycle or timeline. I.e. Quarterly or Annual or reporting. The shortest way to put this is Calendar hours are the combined hours of full time and near full time employees each month of the previous year then averaged for the year to determine "service hours"
                      I searched under Calendar hours/reporting for applicable large employers. This formula is also used to determine employee benefits or employer responsibility and a similar definition is used to determine students credit hours or even professional qualifications.






                      share|improve this answer















                      Work hours are for time to complete task or project by each team or individual. Calendar hours or time is for the whole combined hours of all individuals and processes needed over a period of time to complete more than one project to reach a goal by the end of a predefined cycle or timeline. I.e. Quarterly or Annual or reporting. The shortest way to put this is Calendar hours are the combined hours of full time and near full time employees each month of the previous year then averaged for the year to determine "service hours"
                      I searched under Calendar hours/reporting for applicable large employers. This formula is also used to determine employee benefits or employer responsibility and a similar definition is used to determine students credit hours or even professional qualifications.







                      share|improve this answer















                      share|improve this answer



                      share|improve this answer








                      edited Mar 2 '17 at 15:02


























                      answered Mar 2 '17 at 13:19









                      C.E.B

                      71




                      71







                      • 1




                        is this merely your opinion or you can back it up somehow?
                        – gnat
                        Mar 2 '17 at 13:48










                      • I don't have definitive proof. This is similar to a method That I used myself in construction.
                        – C.E.B
                        Mar 2 '17 at 13:55












                      • 1




                        is this merely your opinion or you can back it up somehow?
                        – gnat
                        Mar 2 '17 at 13:48










                      • I don't have definitive proof. This is similar to a method That I used myself in construction.
                        – C.E.B
                        Mar 2 '17 at 13:55







                      1




                      1




                      is this merely your opinion or you can back it up somehow?
                      – gnat
                      Mar 2 '17 at 13:48




                      is this merely your opinion or you can back it up somehow?
                      – gnat
                      Mar 2 '17 at 13:48












                      I don't have definitive proof. This is similar to a method That I used myself in construction.
                      – C.E.B
                      Mar 2 '17 at 13:55




                      I don't have definitive proof. This is similar to a method That I used myself in construction.
                      – C.E.B
                      Mar 2 '17 at 13:55


                      Comments

                      Popular posts from this blog

                      What does second last employer means? [closed]

                      List of Gilmore Girls characters

                      Confectionery