Self-assessment on “largest project”

The name of the pictureThe name of the pictureThe name of the pictureClash Royale CLAN TAG#URR8PPP





.everyoneloves__top-leaderboard:empty,.everyoneloves__mid-leaderboard:empty margin-bottom:0;







up vote
4
down vote

favorite
1












In the course of applying for positions in software development, I have been asked to indicate the team size and number of lines of code of the largets project I have worked on. Unforunately, while I have been in software development for roughly 10 years, I feel unable to answer this question accurately:



Team size:



I can make a vague guess here. However, the larger the project, the less I ever got in touch with the whole team. Especially the larger projects I was a part of had quite a bit of hierarchical organization, in which I only ever got in touch with representatives of other branches of the project, each of whom spoke for a whole team of developers, whose size I never became aware of.



On top of that, I hardly ever witnessed a project from its first day till its last day. Therefore, I usually do not know how many people contributed to the project in previous or later phases.



Lines of code (LoC):



For similar reasons as above, I simply have no idea how large the projects were I worked on in terms of LoC. Especially in the larger projects, there usually was a clear distribution of responsibilities, in such a way that I usually wouldn't look into code of modules I did not interface with and hence I even have no idea whether most of the other modules were larger or smaller than the modules I was responsible for. Moreover, given that LoC are quite a meaningless metric unless the actual measurement method is well-defined, I never bothered to find out even for the code I wrote myself.



So, how do I answer the question for the largest project in terms of team size and LoC I was involved in?




  • Describe the dimensions of a smaller project? I can tell with absolute certainty that for some of my own open source projects, team size = 1 and LoC = around 50,000 is true. This information would be definitely truthful, but might misrepresent my experience in working on larger projects.


  • Pick an arbitrary, smaller project? This might allow me to make a somewhat accurate guess, but is certainly not answering the question for the largest project.


  • Say I do not know, like in this question. The self-assessment question (on a form ...) does not expect such a long answer. Also, stating briefly "I do not know." might come across as more disinterested in the projects than what I think I am (frankly, I do not see lack of knowledge about team size of LoC any more as a sign of disinterest in a project than lack of knowledge about an author's birth date and age indicates disinterest in their novels) ... or maybe that is just a paranoid fear?






share|improve this question


























    up vote
    4
    down vote

    favorite
    1












    In the course of applying for positions in software development, I have been asked to indicate the team size and number of lines of code of the largets project I have worked on. Unforunately, while I have been in software development for roughly 10 years, I feel unable to answer this question accurately:



    Team size:



    I can make a vague guess here. However, the larger the project, the less I ever got in touch with the whole team. Especially the larger projects I was a part of had quite a bit of hierarchical organization, in which I only ever got in touch with representatives of other branches of the project, each of whom spoke for a whole team of developers, whose size I never became aware of.



    On top of that, I hardly ever witnessed a project from its first day till its last day. Therefore, I usually do not know how many people contributed to the project in previous or later phases.



    Lines of code (LoC):



    For similar reasons as above, I simply have no idea how large the projects were I worked on in terms of LoC. Especially in the larger projects, there usually was a clear distribution of responsibilities, in such a way that I usually wouldn't look into code of modules I did not interface with and hence I even have no idea whether most of the other modules were larger or smaller than the modules I was responsible for. Moreover, given that LoC are quite a meaningless metric unless the actual measurement method is well-defined, I never bothered to find out even for the code I wrote myself.



    So, how do I answer the question for the largest project in terms of team size and LoC I was involved in?




    • Describe the dimensions of a smaller project? I can tell with absolute certainty that for some of my own open source projects, team size = 1 and LoC = around 50,000 is true. This information would be definitely truthful, but might misrepresent my experience in working on larger projects.


    • Pick an arbitrary, smaller project? This might allow me to make a somewhat accurate guess, but is certainly not answering the question for the largest project.


    • Say I do not know, like in this question. The self-assessment question (on a form ...) does not expect such a long answer. Also, stating briefly "I do not know." might come across as more disinterested in the projects than what I think I am (frankly, I do not see lack of knowledge about team size of LoC any more as a sign of disinterest in a project than lack of knowledge about an author's birth date and age indicates disinterest in their novels) ... or maybe that is just a paranoid fear?






    share|improve this question






















      up vote
      4
      down vote

      favorite
      1









      up vote
      4
      down vote

      favorite
      1






      1





      In the course of applying for positions in software development, I have been asked to indicate the team size and number of lines of code of the largets project I have worked on. Unforunately, while I have been in software development for roughly 10 years, I feel unable to answer this question accurately:



      Team size:



      I can make a vague guess here. However, the larger the project, the less I ever got in touch with the whole team. Especially the larger projects I was a part of had quite a bit of hierarchical organization, in which I only ever got in touch with representatives of other branches of the project, each of whom spoke for a whole team of developers, whose size I never became aware of.



      On top of that, I hardly ever witnessed a project from its first day till its last day. Therefore, I usually do not know how many people contributed to the project in previous or later phases.



      Lines of code (LoC):



      For similar reasons as above, I simply have no idea how large the projects were I worked on in terms of LoC. Especially in the larger projects, there usually was a clear distribution of responsibilities, in such a way that I usually wouldn't look into code of modules I did not interface with and hence I even have no idea whether most of the other modules were larger or smaller than the modules I was responsible for. Moreover, given that LoC are quite a meaningless metric unless the actual measurement method is well-defined, I never bothered to find out even for the code I wrote myself.



      So, how do I answer the question for the largest project in terms of team size and LoC I was involved in?




      • Describe the dimensions of a smaller project? I can tell with absolute certainty that for some of my own open source projects, team size = 1 and LoC = around 50,000 is true. This information would be definitely truthful, but might misrepresent my experience in working on larger projects.


      • Pick an arbitrary, smaller project? This might allow me to make a somewhat accurate guess, but is certainly not answering the question for the largest project.


      • Say I do not know, like in this question. The self-assessment question (on a form ...) does not expect such a long answer. Also, stating briefly "I do not know." might come across as more disinterested in the projects than what I think I am (frankly, I do not see lack of knowledge about team size of LoC any more as a sign of disinterest in a project than lack of knowledge about an author's birth date and age indicates disinterest in their novels) ... or maybe that is just a paranoid fear?






      share|improve this question












      In the course of applying for positions in software development, I have been asked to indicate the team size and number of lines of code of the largets project I have worked on. Unforunately, while I have been in software development for roughly 10 years, I feel unable to answer this question accurately:



      Team size:



      I can make a vague guess here. However, the larger the project, the less I ever got in touch with the whole team. Especially the larger projects I was a part of had quite a bit of hierarchical organization, in which I only ever got in touch with representatives of other branches of the project, each of whom spoke for a whole team of developers, whose size I never became aware of.



      On top of that, I hardly ever witnessed a project from its first day till its last day. Therefore, I usually do not know how many people contributed to the project in previous or later phases.



      Lines of code (LoC):



      For similar reasons as above, I simply have no idea how large the projects were I worked on in terms of LoC. Especially in the larger projects, there usually was a clear distribution of responsibilities, in such a way that I usually wouldn't look into code of modules I did not interface with and hence I even have no idea whether most of the other modules were larger or smaller than the modules I was responsible for. Moreover, given that LoC are quite a meaningless metric unless the actual measurement method is well-defined, I never bothered to find out even for the code I wrote myself.



      So, how do I answer the question for the largest project in terms of team size and LoC I was involved in?




      • Describe the dimensions of a smaller project? I can tell with absolute certainty that for some of my own open source projects, team size = 1 and LoC = around 50,000 is true. This information would be definitely truthful, but might misrepresent my experience in working on larger projects.


      • Pick an arbitrary, smaller project? This might allow me to make a somewhat accurate guess, but is certainly not answering the question for the largest project.


      • Say I do not know, like in this question. The self-assessment question (on a form ...) does not expect such a long answer. Also, stating briefly "I do not know." might come across as more disinterested in the projects than what I think I am (frankly, I do not see lack of knowledge about team size of LoC any more as a sign of disinterest in a project than lack of knowledge about an author's birth date and age indicates disinterest in their novels) ... or maybe that is just a paranoid fear?








      share|improve this question











      share|improve this question




      share|improve this question










      asked Dec 6 '15 at 0:57









      user44707

      233




      233




















          4 Answers
          4






          active

          oldest

          votes

















          up vote
          1
          down vote



          accepted










          They ask the team size question to gauge if you worked in a large team or small team. They also gauge if you worked by yourself or with someone else. So you can answer the question appropriately, "I worked with a small team with at least 5 individuals, sometimes more but never over 10. We each get assigned a single ticket for a project each week and we each update our status each morning."



          As for LOC, I never got asked that. I would answer it similar to above, "I contributed roughly 50-1000 lines of code per ticket per week."






          share|improve this answer



























            up vote
            3
            down vote













            I would describe the sections of the project that you actually worked on and state that it was part of a larger project, giving estimates of LoC. If they are familiar with large projects they will find this reasonable. So for instance I worked on X project for a year in a team of ten on the Y section and contributed roughly 50,000 LoC.



            It's not reasonable to expect you to know the exact numbers of staff involved outside your own portion. So give a rough estimate if you have one and stipulate that it is an estimate only.






            share|improve this answer
















            • 1




              I wanted to answer that. Ah, and that LOC are useful only to get an idea of how costly will the maintenance be.
              – gazzz0x2z
              Dec 6 '15 at 7:44






            • 2




              I've never asked or been asked about LoC, I have no idea what meaningful information it gives, I can understand if it's on specifics but otherwise...? Answered a lot of seemingly nonsensical questionnaires over the years though.
              – Kilisi
              Dec 6 '15 at 8:03







            • 3




              People with not much knowledge of softwzre development craft think that LOC are indicative or work done, or total functionalities, or plenty of other things. My experience as maintenance programmer is that it just gives you an idea of the amount of shit you'll have to maintain. 100k LOC is a nice mess, 1M LOC is just hell to take care of alone. Doable, but hell. And of course this is language dependant, I'm speaking COBOL here, limits are probably lower for more expressive languages.
              – gazzz0x2z
              Dec 6 '15 at 8:49

















            up vote
            1
            down vote













            Make an estimate. How would they know any different? Whatever answer seems reasonable to you, that is your answer.



            The bigger issue here is that if you do not know the answers to these questions, then it would call into question your ability to answer similar questions along the same lines. Sure, you can guestimate your way past a total size of project question, but once you start guestimating your way through the whole interview, the other party may start to get the idea you have no idea what you are doing.






            share|improve this answer
















            • 2




              How would they know any different? makes me nervous.
              – cwallenpoole
              Dec 7 '15 at 20:28

















            up vote
            1
            down vote













            I have no idea how many LOC there are in the projects I'm responsible for, but still get asked by interviewees and internal stakeholders. I think it's fine to guesstimate, once past a certain complexity it becomes almost impossible to know. I use the number of bytes in the repo as a proxy for LOC in this extremely clever formula...



            Number of bytes in repo / (Maximum line length in standards / 2)


            Alternatively, you could just write a bit of code to scan your repo and then wait a day while it counts the number of EOLs in there...






            share|improve this answer
















            • 1




              I do not have any access to any of the projects any more that I think are candidates for being the largest ones I have worked on. Otherwise, I certainly could use some method to determine some LoC number (just as I do for my open source projects).
              – user44707
              Dec 6 '15 at 11:13










            Your Answer







            StackExchange.ready(function()
            var channelOptions =
            tags: "".split(" "),
            id: "423"
            ;
            initTagRenderer("".split(" "), "".split(" "), channelOptions);

            StackExchange.using("externalEditor", function()
            // Have to fire editor after snippets, if snippets enabled
            if (StackExchange.settings.snippets.snippetsEnabled)
            StackExchange.using("snippets", function()
            createEditor();
            );

            else
            createEditor();

            );

            function createEditor()
            StackExchange.prepareEditor(
            heartbeatType: 'answer',
            convertImagesToLinks: false,
            noModals: false,
            showLowRepImageUploadWarning: true,
            reputationToPostImages: null,
            bindNavPrevention: true,
            postfix: "",
            noCode: true, onDemand: false,
            discardSelector: ".discard-answer"
            ,immediatelyShowMarkdownHelp:true
            );



            );








             

            draft saved


            draft discarded


















            StackExchange.ready(
            function ()
            StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fworkplace.stackexchange.com%2fquestions%2f58865%2fself-assessment-on-largest-project%23new-answer', 'question_page');

            );

            Post as a guest

























            StackExchange.ready(function ()
            $("#show-editor-button input, #show-editor-button button").click(function ()
            var showEditor = function()
            $("#show-editor-button").hide();
            $("#post-form").removeClass("dno");
            StackExchange.editor.finallyInit();
            ;

            var useFancy = $(this).data('confirm-use-fancy');
            if(useFancy == 'True')
            var popupTitle = $(this).data('confirm-fancy-title');
            var popupBody = $(this).data('confirm-fancy-body');
            var popupAccept = $(this).data('confirm-fancy-accept-button');

            $(this).loadPopup(
            url: '/post/self-answer-popup',
            loaded: function(popup)
            var pTitle = $(popup).find('h2');
            var pBody = $(popup).find('.popup-body');
            var pSubmit = $(popup).find('.popup-submit');

            pTitle.text(popupTitle);
            pBody.html(popupBody);
            pSubmit.val(popupAccept).click(showEditor);

            )
            else
            var confirmText = $(this).data('confirm-text');
            if (confirmText ? confirm(confirmText) : true)
            showEditor();


            );
            );






            4 Answers
            4






            active

            oldest

            votes








            4 Answers
            4






            active

            oldest

            votes









            active

            oldest

            votes






            active

            oldest

            votes








            up vote
            1
            down vote



            accepted










            They ask the team size question to gauge if you worked in a large team or small team. They also gauge if you worked by yourself or with someone else. So you can answer the question appropriately, "I worked with a small team with at least 5 individuals, sometimes more but never over 10. We each get assigned a single ticket for a project each week and we each update our status each morning."



            As for LOC, I never got asked that. I would answer it similar to above, "I contributed roughly 50-1000 lines of code per ticket per week."






            share|improve this answer
























              up vote
              1
              down vote



              accepted










              They ask the team size question to gauge if you worked in a large team or small team. They also gauge if you worked by yourself or with someone else. So you can answer the question appropriately, "I worked with a small team with at least 5 individuals, sometimes more but never over 10. We each get assigned a single ticket for a project each week and we each update our status each morning."



              As for LOC, I never got asked that. I would answer it similar to above, "I contributed roughly 50-1000 lines of code per ticket per week."






              share|improve this answer






















                up vote
                1
                down vote



                accepted







                up vote
                1
                down vote



                accepted






                They ask the team size question to gauge if you worked in a large team or small team. They also gauge if you worked by yourself or with someone else. So you can answer the question appropriately, "I worked with a small team with at least 5 individuals, sometimes more but never over 10. We each get assigned a single ticket for a project each week and we each update our status each morning."



                As for LOC, I never got asked that. I would answer it similar to above, "I contributed roughly 50-1000 lines of code per ticket per week."






                share|improve this answer












                They ask the team size question to gauge if you worked in a large team or small team. They also gauge if you worked by yourself or with someone else. So you can answer the question appropriately, "I worked with a small team with at least 5 individuals, sometimes more but never over 10. We each get assigned a single ticket for a project each week and we each update our status each morning."



                As for LOC, I never got asked that. I would answer it similar to above, "I contributed roughly 50-1000 lines of code per ticket per week."







                share|improve this answer












                share|improve this answer



                share|improve this answer










                answered Dec 7 '15 at 15:43









                Dan

                4,752412




                4,752412






















                    up vote
                    3
                    down vote













                    I would describe the sections of the project that you actually worked on and state that it was part of a larger project, giving estimates of LoC. If they are familiar with large projects they will find this reasonable. So for instance I worked on X project for a year in a team of ten on the Y section and contributed roughly 50,000 LoC.



                    It's not reasonable to expect you to know the exact numbers of staff involved outside your own portion. So give a rough estimate if you have one and stipulate that it is an estimate only.






                    share|improve this answer
















                    • 1




                      I wanted to answer that. Ah, and that LOC are useful only to get an idea of how costly will the maintenance be.
                      – gazzz0x2z
                      Dec 6 '15 at 7:44






                    • 2




                      I've never asked or been asked about LoC, I have no idea what meaningful information it gives, I can understand if it's on specifics but otherwise...? Answered a lot of seemingly nonsensical questionnaires over the years though.
                      – Kilisi
                      Dec 6 '15 at 8:03







                    • 3




                      People with not much knowledge of softwzre development craft think that LOC are indicative or work done, or total functionalities, or plenty of other things. My experience as maintenance programmer is that it just gives you an idea of the amount of shit you'll have to maintain. 100k LOC is a nice mess, 1M LOC is just hell to take care of alone. Doable, but hell. And of course this is language dependant, I'm speaking COBOL here, limits are probably lower for more expressive languages.
                      – gazzz0x2z
                      Dec 6 '15 at 8:49














                    up vote
                    3
                    down vote













                    I would describe the sections of the project that you actually worked on and state that it was part of a larger project, giving estimates of LoC. If they are familiar with large projects they will find this reasonable. So for instance I worked on X project for a year in a team of ten on the Y section and contributed roughly 50,000 LoC.



                    It's not reasonable to expect you to know the exact numbers of staff involved outside your own portion. So give a rough estimate if you have one and stipulate that it is an estimate only.






                    share|improve this answer
















                    • 1




                      I wanted to answer that. Ah, and that LOC are useful only to get an idea of how costly will the maintenance be.
                      – gazzz0x2z
                      Dec 6 '15 at 7:44






                    • 2




                      I've never asked or been asked about LoC, I have no idea what meaningful information it gives, I can understand if it's on specifics but otherwise...? Answered a lot of seemingly nonsensical questionnaires over the years though.
                      – Kilisi
                      Dec 6 '15 at 8:03







                    • 3




                      People with not much knowledge of softwzre development craft think that LOC are indicative or work done, or total functionalities, or plenty of other things. My experience as maintenance programmer is that it just gives you an idea of the amount of shit you'll have to maintain. 100k LOC is a nice mess, 1M LOC is just hell to take care of alone. Doable, but hell. And of course this is language dependant, I'm speaking COBOL here, limits are probably lower for more expressive languages.
                      – gazzz0x2z
                      Dec 6 '15 at 8:49












                    up vote
                    3
                    down vote










                    up vote
                    3
                    down vote









                    I would describe the sections of the project that you actually worked on and state that it was part of a larger project, giving estimates of LoC. If they are familiar with large projects they will find this reasonable. So for instance I worked on X project for a year in a team of ten on the Y section and contributed roughly 50,000 LoC.



                    It's not reasonable to expect you to know the exact numbers of staff involved outside your own portion. So give a rough estimate if you have one and stipulate that it is an estimate only.






                    share|improve this answer












                    I would describe the sections of the project that you actually worked on and state that it was part of a larger project, giving estimates of LoC. If they are familiar with large projects they will find this reasonable. So for instance I worked on X project for a year in a team of ten on the Y section and contributed roughly 50,000 LoC.



                    It's not reasonable to expect you to know the exact numbers of staff involved outside your own portion. So give a rough estimate if you have one and stipulate that it is an estimate only.







                    share|improve this answer












                    share|improve this answer



                    share|improve this answer










                    answered Dec 6 '15 at 1:49









                    Kilisi

                    94.7k50216376




                    94.7k50216376







                    • 1




                      I wanted to answer that. Ah, and that LOC are useful only to get an idea of how costly will the maintenance be.
                      – gazzz0x2z
                      Dec 6 '15 at 7:44






                    • 2




                      I've never asked or been asked about LoC, I have no idea what meaningful information it gives, I can understand if it's on specifics but otherwise...? Answered a lot of seemingly nonsensical questionnaires over the years though.
                      – Kilisi
                      Dec 6 '15 at 8:03







                    • 3




                      People with not much knowledge of softwzre development craft think that LOC are indicative or work done, or total functionalities, or plenty of other things. My experience as maintenance programmer is that it just gives you an idea of the amount of shit you'll have to maintain. 100k LOC is a nice mess, 1M LOC is just hell to take care of alone. Doable, but hell. And of course this is language dependant, I'm speaking COBOL here, limits are probably lower for more expressive languages.
                      – gazzz0x2z
                      Dec 6 '15 at 8:49












                    • 1




                      I wanted to answer that. Ah, and that LOC are useful only to get an idea of how costly will the maintenance be.
                      – gazzz0x2z
                      Dec 6 '15 at 7:44






                    • 2




                      I've never asked or been asked about LoC, I have no idea what meaningful information it gives, I can understand if it's on specifics but otherwise...? Answered a lot of seemingly nonsensical questionnaires over the years though.
                      – Kilisi
                      Dec 6 '15 at 8:03







                    • 3




                      People with not much knowledge of softwzre development craft think that LOC are indicative or work done, or total functionalities, or plenty of other things. My experience as maintenance programmer is that it just gives you an idea of the amount of shit you'll have to maintain. 100k LOC is a nice mess, 1M LOC is just hell to take care of alone. Doable, but hell. And of course this is language dependant, I'm speaking COBOL here, limits are probably lower for more expressive languages.
                      – gazzz0x2z
                      Dec 6 '15 at 8:49







                    1




                    1




                    I wanted to answer that. Ah, and that LOC are useful only to get an idea of how costly will the maintenance be.
                    – gazzz0x2z
                    Dec 6 '15 at 7:44




                    I wanted to answer that. Ah, and that LOC are useful only to get an idea of how costly will the maintenance be.
                    – gazzz0x2z
                    Dec 6 '15 at 7:44




                    2




                    2




                    I've never asked or been asked about LoC, I have no idea what meaningful information it gives, I can understand if it's on specifics but otherwise...? Answered a lot of seemingly nonsensical questionnaires over the years though.
                    – Kilisi
                    Dec 6 '15 at 8:03





                    I've never asked or been asked about LoC, I have no idea what meaningful information it gives, I can understand if it's on specifics but otherwise...? Answered a lot of seemingly nonsensical questionnaires over the years though.
                    – Kilisi
                    Dec 6 '15 at 8:03





                    3




                    3




                    People with not much knowledge of softwzre development craft think that LOC are indicative or work done, or total functionalities, or plenty of other things. My experience as maintenance programmer is that it just gives you an idea of the amount of shit you'll have to maintain. 100k LOC is a nice mess, 1M LOC is just hell to take care of alone. Doable, but hell. And of course this is language dependant, I'm speaking COBOL here, limits are probably lower for more expressive languages.
                    – gazzz0x2z
                    Dec 6 '15 at 8:49




                    People with not much knowledge of softwzre development craft think that LOC are indicative or work done, or total functionalities, or plenty of other things. My experience as maintenance programmer is that it just gives you an idea of the amount of shit you'll have to maintain. 100k LOC is a nice mess, 1M LOC is just hell to take care of alone. Doable, but hell. And of course this is language dependant, I'm speaking COBOL here, limits are probably lower for more expressive languages.
                    – gazzz0x2z
                    Dec 6 '15 at 8:49










                    up vote
                    1
                    down vote













                    Make an estimate. How would they know any different? Whatever answer seems reasonable to you, that is your answer.



                    The bigger issue here is that if you do not know the answers to these questions, then it would call into question your ability to answer similar questions along the same lines. Sure, you can guestimate your way past a total size of project question, but once you start guestimating your way through the whole interview, the other party may start to get the idea you have no idea what you are doing.






                    share|improve this answer
















                    • 2




                      How would they know any different? makes me nervous.
                      – cwallenpoole
                      Dec 7 '15 at 20:28














                    up vote
                    1
                    down vote













                    Make an estimate. How would they know any different? Whatever answer seems reasonable to you, that is your answer.



                    The bigger issue here is that if you do not know the answers to these questions, then it would call into question your ability to answer similar questions along the same lines. Sure, you can guestimate your way past a total size of project question, but once you start guestimating your way through the whole interview, the other party may start to get the idea you have no idea what you are doing.






                    share|improve this answer
















                    • 2




                      How would they know any different? makes me nervous.
                      – cwallenpoole
                      Dec 7 '15 at 20:28












                    up vote
                    1
                    down vote










                    up vote
                    1
                    down vote









                    Make an estimate. How would they know any different? Whatever answer seems reasonable to you, that is your answer.



                    The bigger issue here is that if you do not know the answers to these questions, then it would call into question your ability to answer similar questions along the same lines. Sure, you can guestimate your way past a total size of project question, but once you start guestimating your way through the whole interview, the other party may start to get the idea you have no idea what you are doing.






                    share|improve this answer












                    Make an estimate. How would they know any different? Whatever answer seems reasonable to you, that is your answer.



                    The bigger issue here is that if you do not know the answers to these questions, then it would call into question your ability to answer similar questions along the same lines. Sure, you can guestimate your way past a total size of project question, but once you start guestimating your way through the whole interview, the other party may start to get the idea you have no idea what you are doing.







                    share|improve this answer












                    share|improve this answer



                    share|improve this answer










                    answered Dec 6 '15 at 5:25









                    Socrates

                    5,3951717




                    5,3951717







                    • 2




                      How would they know any different? makes me nervous.
                      – cwallenpoole
                      Dec 7 '15 at 20:28












                    • 2




                      How would they know any different? makes me nervous.
                      – cwallenpoole
                      Dec 7 '15 at 20:28







                    2




                    2




                    How would they know any different? makes me nervous.
                    – cwallenpoole
                    Dec 7 '15 at 20:28




                    How would they know any different? makes me nervous.
                    – cwallenpoole
                    Dec 7 '15 at 20:28










                    up vote
                    1
                    down vote













                    I have no idea how many LOC there are in the projects I'm responsible for, but still get asked by interviewees and internal stakeholders. I think it's fine to guesstimate, once past a certain complexity it becomes almost impossible to know. I use the number of bytes in the repo as a proxy for LOC in this extremely clever formula...



                    Number of bytes in repo / (Maximum line length in standards / 2)


                    Alternatively, you could just write a bit of code to scan your repo and then wait a day while it counts the number of EOLs in there...






                    share|improve this answer
















                    • 1




                      I do not have any access to any of the projects any more that I think are candidates for being the largest ones I have worked on. Otherwise, I certainly could use some method to determine some LoC number (just as I do for my open source projects).
                      – user44707
                      Dec 6 '15 at 11:13














                    up vote
                    1
                    down vote













                    I have no idea how many LOC there are in the projects I'm responsible for, but still get asked by interviewees and internal stakeholders. I think it's fine to guesstimate, once past a certain complexity it becomes almost impossible to know. I use the number of bytes in the repo as a proxy for LOC in this extremely clever formula...



                    Number of bytes in repo / (Maximum line length in standards / 2)


                    Alternatively, you could just write a bit of code to scan your repo and then wait a day while it counts the number of EOLs in there...






                    share|improve this answer
















                    • 1




                      I do not have any access to any of the projects any more that I think are candidates for being the largest ones I have worked on. Otherwise, I certainly could use some method to determine some LoC number (just as I do for my open source projects).
                      – user44707
                      Dec 6 '15 at 11:13












                    up vote
                    1
                    down vote










                    up vote
                    1
                    down vote









                    I have no idea how many LOC there are in the projects I'm responsible for, but still get asked by interviewees and internal stakeholders. I think it's fine to guesstimate, once past a certain complexity it becomes almost impossible to know. I use the number of bytes in the repo as a proxy for LOC in this extremely clever formula...



                    Number of bytes in repo / (Maximum line length in standards / 2)


                    Alternatively, you could just write a bit of code to scan your repo and then wait a day while it counts the number of EOLs in there...






                    share|improve this answer












                    I have no idea how many LOC there are in the projects I'm responsible for, but still get asked by interviewees and internal stakeholders. I think it's fine to guesstimate, once past a certain complexity it becomes almost impossible to know. I use the number of bytes in the repo as a proxy for LOC in this extremely clever formula...



                    Number of bytes in repo / (Maximum line length in standards / 2)


                    Alternatively, you could just write a bit of code to scan your repo and then wait a day while it counts the number of EOLs in there...







                    share|improve this answer












                    share|improve this answer



                    share|improve this answer










                    answered Dec 6 '15 at 7:06









                    Ben

                    99211320




                    99211320







                    • 1




                      I do not have any access to any of the projects any more that I think are candidates for being the largest ones I have worked on. Otherwise, I certainly could use some method to determine some LoC number (just as I do for my open source projects).
                      – user44707
                      Dec 6 '15 at 11:13












                    • 1




                      I do not have any access to any of the projects any more that I think are candidates for being the largest ones I have worked on. Otherwise, I certainly could use some method to determine some LoC number (just as I do for my open source projects).
                      – user44707
                      Dec 6 '15 at 11:13







                    1




                    1




                    I do not have any access to any of the projects any more that I think are candidates for being the largest ones I have worked on. Otherwise, I certainly could use some method to determine some LoC number (just as I do for my open source projects).
                    – user44707
                    Dec 6 '15 at 11:13




                    I do not have any access to any of the projects any more that I think are candidates for being the largest ones I have worked on. Otherwise, I certainly could use some method to determine some LoC number (just as I do for my open source projects).
                    – user44707
                    Dec 6 '15 at 11:13












                     

                    draft saved


                    draft discarded


























                     


                    draft saved


                    draft discarded














                    StackExchange.ready(
                    function ()
                    StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fworkplace.stackexchange.com%2fquestions%2f58865%2fself-assessment-on-largest-project%23new-answer', 'question_page');

                    );

                    Post as a guest

















































































                    Comments

                    Popular posts from this blog

                    What does second last employer means? [closed]

                    List of Gilmore Girls characters

                    Confectionery