How to respond to your boss when he ask what took so long to finish a project?
Clash Royale CLAN TAG#URR8PPP
.everyoneloves__top-leaderboard:empty,.everyoneloves__mid-leaderboard:empty margin-bottom:0;
up vote
2
down vote
favorite
I was assigned multiple projects at work and one of the projects my boss is asking what took so long to complete. The project he is referring to was reassigned to me with not enough information to start and because I was busy with other projects I did not follow-up to get all the details. Once I received all the details I was able to complete the project quickly but only after he sent an email asking why its not completed. After I finished the project he sent another email asking what took so long. I am not really sure how to respond to that.
professionalism time-management manager projects
suggest improvements |Â
up vote
2
down vote
favorite
I was assigned multiple projects at work and one of the projects my boss is asking what took so long to complete. The project he is referring to was reassigned to me with not enough information to start and because I was busy with other projects I did not follow-up to get all the details. Once I received all the details I was able to complete the project quickly but only after he sent an email asking why its not completed. After I finished the project he sent another email asking what took so long. I am not really sure how to respond to that.
professionalism time-management manager projects
8
Telling the facts?
– Jan Doggen
Sep 18 '14 at 7:00
Did the over-all project take too long or does he feel each task should have been completed in the same amount of time (i.e. You may have been slacking off on some the projects.)?
– user8365
Sep 18 '14 at 13:36
1
Usually, the best answer is just telling the truth. The more important question is: why is he asking you AFTER the project is finished ?
– Radu Murzea
Sep 18 '14 at 21:00
suggest improvements |Â
up vote
2
down vote
favorite
up vote
2
down vote
favorite
I was assigned multiple projects at work and one of the projects my boss is asking what took so long to complete. The project he is referring to was reassigned to me with not enough information to start and because I was busy with other projects I did not follow-up to get all the details. Once I received all the details I was able to complete the project quickly but only after he sent an email asking why its not completed. After I finished the project he sent another email asking what took so long. I am not really sure how to respond to that.
professionalism time-management manager projects
I was assigned multiple projects at work and one of the projects my boss is asking what took so long to complete. The project he is referring to was reassigned to me with not enough information to start and because I was busy with other projects I did not follow-up to get all the details. Once I received all the details I was able to complete the project quickly but only after he sent an email asking why its not completed. After I finished the project he sent another email asking what took so long. I am not really sure how to respond to that.
professionalism time-management manager projects
edited Sep 18 '14 at 20:35
asked Sep 18 '14 at 5:15
Project Watchers
17113
17113
8
Telling the facts?
– Jan Doggen
Sep 18 '14 at 7:00
Did the over-all project take too long or does he feel each task should have been completed in the same amount of time (i.e. You may have been slacking off on some the projects.)?
– user8365
Sep 18 '14 at 13:36
1
Usually, the best answer is just telling the truth. The more important question is: why is he asking you AFTER the project is finished ?
– Radu Murzea
Sep 18 '14 at 21:00
suggest improvements |Â
8
Telling the facts?
– Jan Doggen
Sep 18 '14 at 7:00
Did the over-all project take too long or does he feel each task should have been completed in the same amount of time (i.e. You may have been slacking off on some the projects.)?
– user8365
Sep 18 '14 at 13:36
1
Usually, the best answer is just telling the truth. The more important question is: why is he asking you AFTER the project is finished ?
– Radu Murzea
Sep 18 '14 at 21:00
8
8
Telling the facts?
– Jan Doggen
Sep 18 '14 at 7:00
Telling the facts?
– Jan Doggen
Sep 18 '14 at 7:00
Did the over-all project take too long or does he feel each task should have been completed in the same amount of time (i.e. You may have been slacking off on some the projects.)?
– user8365
Sep 18 '14 at 13:36
Did the over-all project take too long or does he feel each task should have been completed in the same amount of time (i.e. You may have been slacking off on some the projects.)?
– user8365
Sep 18 '14 at 13:36
1
1
Usually, the best answer is just telling the truth. The more important question is: why is he asking you AFTER the project is finished ?
– Radu Murzea
Sep 18 '14 at 21:00
Usually, the best answer is just telling the truth. The more important question is: why is he asking you AFTER the project is finished ?
– Radu Murzea
Sep 18 '14 at 21:00
suggest improvements |Â
4 Answers
4
active
oldest
votes
up vote
8
down vote
First, you need to realize that when your boss asks you this, you already have a problem. You are in a hole now and it's important to do the right thing to get out of it.
Back when things started to slip from your plan and your schedule, you needed to inform your boss, things like "I still don't have xyz from abc so we are now going to be late with def" or "the reports have taken a lot longer than I expected, so I'm two weeks behind, and I don't think I'll be able to make that up while I do the rest of the project, so it will finish two weeks late." Or perhaps when your boss asked you to take on an extra task, you could have replied "I can do that, but it will delay my work on ghi by at least a week." Bosses don't always keep track of all the moving parts, and may assume that you accepting work means that you have time for it in your current workload.
I hope you took good notes and know what the issues were. As your boss, I would be interested in knowing what we need to do to prevent this next time. Is it that you took more work hours to complete the task than I thought it would take? Is it that you were blocked or delayed by other people so it took more elapsed time? Is it that you have a lot of things to do so you weren't able to put time in on this project? Is it that you just plain don't work hard enough? Without whining or making excuses, you need to clearly demonstrate what happened. Pay attention to measurable facts like:
- the original estimates or guidelines or deadlines you were given for each task. Both the effort (eg 40 hours) and the elapsed time (eg two weeks if you put half your time into it.)
- the actual effort and elapsed time you spent
- any delays where you couldn't work on it at all, or enough, and why
- any rework or times when you spent more effort than you had planned to, and why
- any reporting you did to your boss about delays, extra effort, or other work keeping you from getting to this work
It would probably help if you also had a plan for what you will do in the future to prevent this, such as reporting delays caused by others more quickly, not planning to put 8 hours a day on a project when you know you will have support duties while you're doing the project, getting some training on something you're slow at, and so on. If some of that plan has already been put into motion, even better.
Thanks Kate. Really good feedback and you made some really good points.
– Project Watchers
Sep 19 '14 at 3:42
suggest improvements |Â
up vote
6
down vote
Answer it factually. List what he assigned you and the priorities those tasks were given, list how much time each one took and (as exactly as possible) why it took that much time (remember to include time lost to things like mandatory meetings), and ask him whether he can offer suggestions that might speed it up next time, or how priorities can be better set/recognized/communicated next time, or whether there's a better way to estimate how long a group of tasks will take to complete.
It's his job to push you to improve, but also his job to guide you toward improvement.
If you take the time to put together a reasonable answer, you usually don't have to be afraid of this question.
LATE ADDITION:
If you continue to be overloaded and expect it to be an issue again, a useful pattern is "Sure, I can take that on, but since I'm already at capacity something else is going to have to slip to make room. What's its priority relative to...?" Don't invoke it when you don't need to, but don't promise more than you believe you can accomplish either.
It's his job to push you to improve, but also his job to guide you toward improvement.
In a healthy organization, 'Yes' - This is correct; but the OP may not be in a healthy organization and his/her both may simply be playing CYA. // In any event, the rest of your answer is solid.
– Jim G.
Sep 18 '14 at 6:41
@JimG. - Granted. However, even in that case, this is the best bet to defuse him.
– keshlam
Sep 18 '14 at 12:38
suggest improvements |Â
up vote
3
down vote
List the issues and challenges that you ran into while completing the project, what you did to resolve them, why the resolution process took time e.g. you had to work out an answer from scratch and you had to test to validate it and of course, you had to work out how to design the tests. You can conclude that some of the issues and challenges (list them) were one-offs i.e. you know what you have to do the next time and that others ares bound to recur (list them).
Be clinical, dispassionate and thorough - This is how you are communicating that you are competent. Make no excuses, if you screwed up somewhere, say so. Better some damage to your boss's high perception of you than losing your credibility with the boss - You want to get to the point where if there were a FUBAR and you had nothing to do with it, he takes your word without a murmur.
Next time:
Keep track of how long your projects are taking. If one or more of your projects falls behind schedule, notify your boss immediately and tell him what the challenge is - the boss has resources to back you up that you don't have, and he can make decisions that you can't make e.g. postponing the project, putting it on a lower priority or putting other projects on a lower priority so that you can complete this project on time, or extending the deadline on your project. I suspect that you failed to keep the lines of communication open with your boss regarding your progress on your projects and that's why he is now asking for an accounting.
suggest improvements |Â
up vote
3
down vote
I can't see why different projects taking different time to finish would be surprising to your boss. They are, by definition, not the same. If some took longer than planned, that's a different issue.
Either way, stick to the facts. From what you're saying (btw you might want to edit and add a few more details so we can answer you better) there is no reason to assume your boss is asking in an "hostile" way (like "ok, so where did you fuck up?"). Maybe he just wants to know what happened so he can plan things more accurately next time, and/or divide the tasks in a more efficient way
suggest improvements |Â
StackExchange.ready(function ()
$("#show-editor-button input, #show-editor-button button").click(function ()
var showEditor = function()
$("#show-editor-button").hide();
$("#post-form").removeClass("dno");
StackExchange.editor.finallyInit();
;
var useFancy = $(this).data('confirm-use-fancy');
if(useFancy == 'True')
var popupTitle = $(this).data('confirm-fancy-title');
var popupBody = $(this).data('confirm-fancy-body');
var popupAccept = $(this).data('confirm-fancy-accept-button');
$(this).loadPopup(
url: '/post/self-answer-popup',
loaded: function(popup)
var pTitle = $(popup).find('h2');
var pBody = $(popup).find('.popup-body');
var pSubmit = $(popup).find('.popup-submit');
pTitle.text(popupTitle);
pBody.html(popupBody);
pSubmit.val(popupAccept).click(showEditor);
)
else
var confirmText = $(this).data('confirm-text');
if (confirmText ? confirm(confirmText) : true)
showEditor();
);
);
4 Answers
4
active
oldest
votes
4 Answers
4
active
oldest
votes
active
oldest
votes
active
oldest
votes
up vote
8
down vote
First, you need to realize that when your boss asks you this, you already have a problem. You are in a hole now and it's important to do the right thing to get out of it.
Back when things started to slip from your plan and your schedule, you needed to inform your boss, things like "I still don't have xyz from abc so we are now going to be late with def" or "the reports have taken a lot longer than I expected, so I'm two weeks behind, and I don't think I'll be able to make that up while I do the rest of the project, so it will finish two weeks late." Or perhaps when your boss asked you to take on an extra task, you could have replied "I can do that, but it will delay my work on ghi by at least a week." Bosses don't always keep track of all the moving parts, and may assume that you accepting work means that you have time for it in your current workload.
I hope you took good notes and know what the issues were. As your boss, I would be interested in knowing what we need to do to prevent this next time. Is it that you took more work hours to complete the task than I thought it would take? Is it that you were blocked or delayed by other people so it took more elapsed time? Is it that you have a lot of things to do so you weren't able to put time in on this project? Is it that you just plain don't work hard enough? Without whining or making excuses, you need to clearly demonstrate what happened. Pay attention to measurable facts like:
- the original estimates or guidelines or deadlines you were given for each task. Both the effort (eg 40 hours) and the elapsed time (eg two weeks if you put half your time into it.)
- the actual effort and elapsed time you spent
- any delays where you couldn't work on it at all, or enough, and why
- any rework or times when you spent more effort than you had planned to, and why
- any reporting you did to your boss about delays, extra effort, or other work keeping you from getting to this work
It would probably help if you also had a plan for what you will do in the future to prevent this, such as reporting delays caused by others more quickly, not planning to put 8 hours a day on a project when you know you will have support duties while you're doing the project, getting some training on something you're slow at, and so on. If some of that plan has already been put into motion, even better.
Thanks Kate. Really good feedback and you made some really good points.
– Project Watchers
Sep 19 '14 at 3:42
suggest improvements |Â
up vote
8
down vote
First, you need to realize that when your boss asks you this, you already have a problem. You are in a hole now and it's important to do the right thing to get out of it.
Back when things started to slip from your plan and your schedule, you needed to inform your boss, things like "I still don't have xyz from abc so we are now going to be late with def" or "the reports have taken a lot longer than I expected, so I'm two weeks behind, and I don't think I'll be able to make that up while I do the rest of the project, so it will finish two weeks late." Or perhaps when your boss asked you to take on an extra task, you could have replied "I can do that, but it will delay my work on ghi by at least a week." Bosses don't always keep track of all the moving parts, and may assume that you accepting work means that you have time for it in your current workload.
I hope you took good notes and know what the issues were. As your boss, I would be interested in knowing what we need to do to prevent this next time. Is it that you took more work hours to complete the task than I thought it would take? Is it that you were blocked or delayed by other people so it took more elapsed time? Is it that you have a lot of things to do so you weren't able to put time in on this project? Is it that you just plain don't work hard enough? Without whining or making excuses, you need to clearly demonstrate what happened. Pay attention to measurable facts like:
- the original estimates or guidelines or deadlines you were given for each task. Both the effort (eg 40 hours) and the elapsed time (eg two weeks if you put half your time into it.)
- the actual effort and elapsed time you spent
- any delays where you couldn't work on it at all, or enough, and why
- any rework or times when you spent more effort than you had planned to, and why
- any reporting you did to your boss about delays, extra effort, or other work keeping you from getting to this work
It would probably help if you also had a plan for what you will do in the future to prevent this, such as reporting delays caused by others more quickly, not planning to put 8 hours a day on a project when you know you will have support duties while you're doing the project, getting some training on something you're slow at, and so on. If some of that plan has already been put into motion, even better.
Thanks Kate. Really good feedback and you made some really good points.
– Project Watchers
Sep 19 '14 at 3:42
suggest improvements |Â
up vote
8
down vote
up vote
8
down vote
First, you need to realize that when your boss asks you this, you already have a problem. You are in a hole now and it's important to do the right thing to get out of it.
Back when things started to slip from your plan and your schedule, you needed to inform your boss, things like "I still don't have xyz from abc so we are now going to be late with def" or "the reports have taken a lot longer than I expected, so I'm two weeks behind, and I don't think I'll be able to make that up while I do the rest of the project, so it will finish two weeks late." Or perhaps when your boss asked you to take on an extra task, you could have replied "I can do that, but it will delay my work on ghi by at least a week." Bosses don't always keep track of all the moving parts, and may assume that you accepting work means that you have time for it in your current workload.
I hope you took good notes and know what the issues were. As your boss, I would be interested in knowing what we need to do to prevent this next time. Is it that you took more work hours to complete the task than I thought it would take? Is it that you were blocked or delayed by other people so it took more elapsed time? Is it that you have a lot of things to do so you weren't able to put time in on this project? Is it that you just plain don't work hard enough? Without whining or making excuses, you need to clearly demonstrate what happened. Pay attention to measurable facts like:
- the original estimates or guidelines or deadlines you were given for each task. Both the effort (eg 40 hours) and the elapsed time (eg two weeks if you put half your time into it.)
- the actual effort and elapsed time you spent
- any delays where you couldn't work on it at all, or enough, and why
- any rework or times when you spent more effort than you had planned to, and why
- any reporting you did to your boss about delays, extra effort, or other work keeping you from getting to this work
It would probably help if you also had a plan for what you will do in the future to prevent this, such as reporting delays caused by others more quickly, not planning to put 8 hours a day on a project when you know you will have support duties while you're doing the project, getting some training on something you're slow at, and so on. If some of that plan has already been put into motion, even better.
First, you need to realize that when your boss asks you this, you already have a problem. You are in a hole now and it's important to do the right thing to get out of it.
Back when things started to slip from your plan and your schedule, you needed to inform your boss, things like "I still don't have xyz from abc so we are now going to be late with def" or "the reports have taken a lot longer than I expected, so I'm two weeks behind, and I don't think I'll be able to make that up while I do the rest of the project, so it will finish two weeks late." Or perhaps when your boss asked you to take on an extra task, you could have replied "I can do that, but it will delay my work on ghi by at least a week." Bosses don't always keep track of all the moving parts, and may assume that you accepting work means that you have time for it in your current workload.
I hope you took good notes and know what the issues were. As your boss, I would be interested in knowing what we need to do to prevent this next time. Is it that you took more work hours to complete the task than I thought it would take? Is it that you were blocked or delayed by other people so it took more elapsed time? Is it that you have a lot of things to do so you weren't able to put time in on this project? Is it that you just plain don't work hard enough? Without whining or making excuses, you need to clearly demonstrate what happened. Pay attention to measurable facts like:
- the original estimates or guidelines or deadlines you were given for each task. Both the effort (eg 40 hours) and the elapsed time (eg two weeks if you put half your time into it.)
- the actual effort and elapsed time you spent
- any delays where you couldn't work on it at all, or enough, and why
- any rework or times when you spent more effort than you had planned to, and why
- any reporting you did to your boss about delays, extra effort, or other work keeping you from getting to this work
It would probably help if you also had a plan for what you will do in the future to prevent this, such as reporting delays caused by others more quickly, not planning to put 8 hours a day on a project when you know you will have support duties while you're doing the project, getting some training on something you're slow at, and so on. If some of that plan has already been put into motion, even better.
answered Sep 18 '14 at 15:17
Kate Gregory
105k40232334
105k40232334
Thanks Kate. Really good feedback and you made some really good points.
– Project Watchers
Sep 19 '14 at 3:42
suggest improvements |Â
Thanks Kate. Really good feedback and you made some really good points.
– Project Watchers
Sep 19 '14 at 3:42
Thanks Kate. Really good feedback and you made some really good points.
– Project Watchers
Sep 19 '14 at 3:42
Thanks Kate. Really good feedback and you made some really good points.
– Project Watchers
Sep 19 '14 at 3:42
suggest improvements |Â
up vote
6
down vote
Answer it factually. List what he assigned you and the priorities those tasks were given, list how much time each one took and (as exactly as possible) why it took that much time (remember to include time lost to things like mandatory meetings), and ask him whether he can offer suggestions that might speed it up next time, or how priorities can be better set/recognized/communicated next time, or whether there's a better way to estimate how long a group of tasks will take to complete.
It's his job to push you to improve, but also his job to guide you toward improvement.
If you take the time to put together a reasonable answer, you usually don't have to be afraid of this question.
LATE ADDITION:
If you continue to be overloaded and expect it to be an issue again, a useful pattern is "Sure, I can take that on, but since I'm already at capacity something else is going to have to slip to make room. What's its priority relative to...?" Don't invoke it when you don't need to, but don't promise more than you believe you can accomplish either.
It's his job to push you to improve, but also his job to guide you toward improvement.
In a healthy organization, 'Yes' - This is correct; but the OP may not be in a healthy organization and his/her both may simply be playing CYA. // In any event, the rest of your answer is solid.
– Jim G.
Sep 18 '14 at 6:41
@JimG. - Granted. However, even in that case, this is the best bet to defuse him.
– keshlam
Sep 18 '14 at 12:38
suggest improvements |Â
up vote
6
down vote
Answer it factually. List what he assigned you and the priorities those tasks were given, list how much time each one took and (as exactly as possible) why it took that much time (remember to include time lost to things like mandatory meetings), and ask him whether he can offer suggestions that might speed it up next time, or how priorities can be better set/recognized/communicated next time, or whether there's a better way to estimate how long a group of tasks will take to complete.
It's his job to push you to improve, but also his job to guide you toward improvement.
If you take the time to put together a reasonable answer, you usually don't have to be afraid of this question.
LATE ADDITION:
If you continue to be overloaded and expect it to be an issue again, a useful pattern is "Sure, I can take that on, but since I'm already at capacity something else is going to have to slip to make room. What's its priority relative to...?" Don't invoke it when you don't need to, but don't promise more than you believe you can accomplish either.
It's his job to push you to improve, but also his job to guide you toward improvement.
In a healthy organization, 'Yes' - This is correct; but the OP may not be in a healthy organization and his/her both may simply be playing CYA. // In any event, the rest of your answer is solid.
– Jim G.
Sep 18 '14 at 6:41
@JimG. - Granted. However, even in that case, this is the best bet to defuse him.
– keshlam
Sep 18 '14 at 12:38
suggest improvements |Â
up vote
6
down vote
up vote
6
down vote
Answer it factually. List what he assigned you and the priorities those tasks were given, list how much time each one took and (as exactly as possible) why it took that much time (remember to include time lost to things like mandatory meetings), and ask him whether he can offer suggestions that might speed it up next time, or how priorities can be better set/recognized/communicated next time, or whether there's a better way to estimate how long a group of tasks will take to complete.
It's his job to push you to improve, but also his job to guide you toward improvement.
If you take the time to put together a reasonable answer, you usually don't have to be afraid of this question.
LATE ADDITION:
If you continue to be overloaded and expect it to be an issue again, a useful pattern is "Sure, I can take that on, but since I'm already at capacity something else is going to have to slip to make room. What's its priority relative to...?" Don't invoke it when you don't need to, but don't promise more than you believe you can accomplish either.
Answer it factually. List what he assigned you and the priorities those tasks were given, list how much time each one took and (as exactly as possible) why it took that much time (remember to include time lost to things like mandatory meetings), and ask him whether he can offer suggestions that might speed it up next time, or how priorities can be better set/recognized/communicated next time, or whether there's a better way to estimate how long a group of tasks will take to complete.
It's his job to push you to improve, but also his job to guide you toward improvement.
If you take the time to put together a reasonable answer, you usually don't have to be afraid of this question.
LATE ADDITION:
If you continue to be overloaded and expect it to be an issue again, a useful pattern is "Sure, I can take that on, but since I'm already at capacity something else is going to have to slip to make room. What's its priority relative to...?" Don't invoke it when you don't need to, but don't promise more than you believe you can accomplish either.
edited Sep 18 '14 at 12:45
answered Sep 18 '14 at 5:58
keshlam
41.5k1267144
41.5k1267144
It's his job to push you to improve, but also his job to guide you toward improvement.
In a healthy organization, 'Yes' - This is correct; but the OP may not be in a healthy organization and his/her both may simply be playing CYA. // In any event, the rest of your answer is solid.
– Jim G.
Sep 18 '14 at 6:41
@JimG. - Granted. However, even in that case, this is the best bet to defuse him.
– keshlam
Sep 18 '14 at 12:38
suggest improvements |Â
It's his job to push you to improve, but also his job to guide you toward improvement.
In a healthy organization, 'Yes' - This is correct; but the OP may not be in a healthy organization and his/her both may simply be playing CYA. // In any event, the rest of your answer is solid.
– Jim G.
Sep 18 '14 at 6:41
@JimG. - Granted. However, even in that case, this is the best bet to defuse him.
– keshlam
Sep 18 '14 at 12:38
It's his job to push you to improve, but also his job to guide you toward improvement.
In a healthy organization, 'Yes' - This is correct; but the OP may not be in a healthy organization and his/her both may simply be playing CYA. // In any event, the rest of your answer is solid.– Jim G.
Sep 18 '14 at 6:41
It's his job to push you to improve, but also his job to guide you toward improvement.
In a healthy organization, 'Yes' - This is correct; but the OP may not be in a healthy organization and his/her both may simply be playing CYA. // In any event, the rest of your answer is solid.– Jim G.
Sep 18 '14 at 6:41
@JimG. - Granted. However, even in that case, this is the best bet to defuse him.
– keshlam
Sep 18 '14 at 12:38
@JimG. - Granted. However, even in that case, this is the best bet to defuse him.
– keshlam
Sep 18 '14 at 12:38
suggest improvements |Â
up vote
3
down vote
List the issues and challenges that you ran into while completing the project, what you did to resolve them, why the resolution process took time e.g. you had to work out an answer from scratch and you had to test to validate it and of course, you had to work out how to design the tests. You can conclude that some of the issues and challenges (list them) were one-offs i.e. you know what you have to do the next time and that others ares bound to recur (list them).
Be clinical, dispassionate and thorough - This is how you are communicating that you are competent. Make no excuses, if you screwed up somewhere, say so. Better some damage to your boss's high perception of you than losing your credibility with the boss - You want to get to the point where if there were a FUBAR and you had nothing to do with it, he takes your word without a murmur.
Next time:
Keep track of how long your projects are taking. If one or more of your projects falls behind schedule, notify your boss immediately and tell him what the challenge is - the boss has resources to back you up that you don't have, and he can make decisions that you can't make e.g. postponing the project, putting it on a lower priority or putting other projects on a lower priority so that you can complete this project on time, or extending the deadline on your project. I suspect that you failed to keep the lines of communication open with your boss regarding your progress on your projects and that's why he is now asking for an accounting.
suggest improvements |Â
up vote
3
down vote
List the issues and challenges that you ran into while completing the project, what you did to resolve them, why the resolution process took time e.g. you had to work out an answer from scratch and you had to test to validate it and of course, you had to work out how to design the tests. You can conclude that some of the issues and challenges (list them) were one-offs i.e. you know what you have to do the next time and that others ares bound to recur (list them).
Be clinical, dispassionate and thorough - This is how you are communicating that you are competent. Make no excuses, if you screwed up somewhere, say so. Better some damage to your boss's high perception of you than losing your credibility with the boss - You want to get to the point where if there were a FUBAR and you had nothing to do with it, he takes your word without a murmur.
Next time:
Keep track of how long your projects are taking. If one or more of your projects falls behind schedule, notify your boss immediately and tell him what the challenge is - the boss has resources to back you up that you don't have, and he can make decisions that you can't make e.g. postponing the project, putting it on a lower priority or putting other projects on a lower priority so that you can complete this project on time, or extending the deadline on your project. I suspect that you failed to keep the lines of communication open with your boss regarding your progress on your projects and that's why he is now asking for an accounting.
suggest improvements |Â
up vote
3
down vote
up vote
3
down vote
List the issues and challenges that you ran into while completing the project, what you did to resolve them, why the resolution process took time e.g. you had to work out an answer from scratch and you had to test to validate it and of course, you had to work out how to design the tests. You can conclude that some of the issues and challenges (list them) were one-offs i.e. you know what you have to do the next time and that others ares bound to recur (list them).
Be clinical, dispassionate and thorough - This is how you are communicating that you are competent. Make no excuses, if you screwed up somewhere, say so. Better some damage to your boss's high perception of you than losing your credibility with the boss - You want to get to the point where if there were a FUBAR and you had nothing to do with it, he takes your word without a murmur.
Next time:
Keep track of how long your projects are taking. If one or more of your projects falls behind schedule, notify your boss immediately and tell him what the challenge is - the boss has resources to back you up that you don't have, and he can make decisions that you can't make e.g. postponing the project, putting it on a lower priority or putting other projects on a lower priority so that you can complete this project on time, or extending the deadline on your project. I suspect that you failed to keep the lines of communication open with your boss regarding your progress on your projects and that's why he is now asking for an accounting.
List the issues and challenges that you ran into while completing the project, what you did to resolve them, why the resolution process took time e.g. you had to work out an answer from scratch and you had to test to validate it and of course, you had to work out how to design the tests. You can conclude that some of the issues and challenges (list them) were one-offs i.e. you know what you have to do the next time and that others ares bound to recur (list them).
Be clinical, dispassionate and thorough - This is how you are communicating that you are competent. Make no excuses, if you screwed up somewhere, say so. Better some damage to your boss's high perception of you than losing your credibility with the boss - You want to get to the point where if there were a FUBAR and you had nothing to do with it, he takes your word without a murmur.
Next time:
Keep track of how long your projects are taking. If one or more of your projects falls behind schedule, notify your boss immediately and tell him what the challenge is - the boss has resources to back you up that you don't have, and he can make decisions that you can't make e.g. postponing the project, putting it on a lower priority or putting other projects on a lower priority so that you can complete this project on time, or extending the deadline on your project. I suspect that you failed to keep the lines of communication open with your boss regarding your progress on your projects and that's why he is now asking for an accounting.
edited Sep 18 '14 at 11:12
answered Sep 18 '14 at 11:03
Vietnhi Phuvan
68.9k7118254
68.9k7118254
suggest improvements |Â
suggest improvements |Â
up vote
3
down vote
I can't see why different projects taking different time to finish would be surprising to your boss. They are, by definition, not the same. If some took longer than planned, that's a different issue.
Either way, stick to the facts. From what you're saying (btw you might want to edit and add a few more details so we can answer you better) there is no reason to assume your boss is asking in an "hostile" way (like "ok, so where did you fuck up?"). Maybe he just wants to know what happened so he can plan things more accurately next time, and/or divide the tasks in a more efficient way
suggest improvements |Â
up vote
3
down vote
I can't see why different projects taking different time to finish would be surprising to your boss. They are, by definition, not the same. If some took longer than planned, that's a different issue.
Either way, stick to the facts. From what you're saying (btw you might want to edit and add a few more details so we can answer you better) there is no reason to assume your boss is asking in an "hostile" way (like "ok, so where did you fuck up?"). Maybe he just wants to know what happened so he can plan things more accurately next time, and/or divide the tasks in a more efficient way
suggest improvements |Â
up vote
3
down vote
up vote
3
down vote
I can't see why different projects taking different time to finish would be surprising to your boss. They are, by definition, not the same. If some took longer than planned, that's a different issue.
Either way, stick to the facts. From what you're saying (btw you might want to edit and add a few more details so we can answer you better) there is no reason to assume your boss is asking in an "hostile" way (like "ok, so where did you fuck up?"). Maybe he just wants to know what happened so he can plan things more accurately next time, and/or divide the tasks in a more efficient way
I can't see why different projects taking different time to finish would be surprising to your boss. They are, by definition, not the same. If some took longer than planned, that's a different issue.
Either way, stick to the facts. From what you're saying (btw you might want to edit and add a few more details so we can answer you better) there is no reason to assume your boss is asking in an "hostile" way (like "ok, so where did you fuck up?"). Maybe he just wants to know what happened so he can plan things more accurately next time, and/or divide the tasks in a more efficient way
answered Sep 18 '14 at 11:30
ero
1,67468
1,67468
suggest improvements |Â
suggest improvements |Â
Sign up or log in
StackExchange.ready(function ()
StackExchange.helpers.onClickDraftSave('#login-link');
);
Sign up using Google
Sign up using Facebook
Sign up using Email and Password
Post as a guest
StackExchange.ready(
function ()
StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fworkplace.stackexchange.com%2fquestions%2f33912%2fhow-to-respond-to-your-boss-when-he-ask-what-took-so-long-to-finish-a-project%23new-answer', 'question_page');
);
Post as a guest
Sign up or log in
StackExchange.ready(function ()
StackExchange.helpers.onClickDraftSave('#login-link');
);
Sign up using Google
Sign up using Facebook
Sign up using Email and Password
Post as a guest
Sign up or log in
StackExchange.ready(function ()
StackExchange.helpers.onClickDraftSave('#login-link');
);
Sign up using Google
Sign up using Facebook
Sign up using Email and Password
Post as a guest
Sign up or log in
StackExchange.ready(function ()
StackExchange.helpers.onClickDraftSave('#login-link');
);
Sign up using Google
Sign up using Facebook
Sign up using Email and Password
Sign up using Google
Sign up using Facebook
Sign up using Email and Password
8
Telling the facts?
– Jan Doggen
Sep 18 '14 at 7:00
Did the over-all project take too long or does he feel each task should have been completed in the same amount of time (i.e. You may have been slacking off on some the projects.)?
– user8365
Sep 18 '14 at 13:36
1
Usually, the best answer is just telling the truth. The more important question is: why is he asking you AFTER the project is finished ?
– Radu Murzea
Sep 18 '14 at 21:00